(BEDFORD) - Good weather has been helping workers at the Bedford Public Library.
Progress on the parking lot, new book drop and new entrance is running very smoothly according to director Susan Miller.
Miller says barring any severe weather, the outside projects should be completed by mid-August.
Right now they are also cleaning and repointing the limestone on the building and should replace the sidewalks by next week on the south side of the library.
Work on the inside of the building should be finished by November.