Brought to you by WBIW News and Network Indiana
Last updated on Thursday, April 12, 2018
(ODON) - The construction on the Odon-Cannelburg Road Project hit a snag when an unidentified Odon waterline was discovered in the construction zone.
Previous meetings with INDOT has identified and accounted for potential problems and INDOT won't allow the cost of moving the recently found waterline to be part of the road project. This means the Town of Odon is responsible for the entire $15,000 cost.
The Daviess County Commissioners told members of the Odon Town Board that the County would try to find funds to pay half the costs.
County Engineer Jason Heile says concrete paving will start on the Odon-Cannelburg Road project today. The road will be closed to traffic in the construction area.
Heile reported the Washington 15th Street Bridge project is proceeding on schedule. The old bridge has been removed and crews are preparing to set the foundation for the new bridge. The bridge should be completed by November 7 weather permitting.
1340 AM WBIW welcomes comments and suggestions by calling 812.277.1340 during normal business hours or by email at comments@wbiw.com