Bloomington’s Bicentennial gateway construction begins August 5

BLOOMINGTON– Bloomington Parks and Recreation on July 30 received the necessary approvals for temporary vehicle lane and cut-through closures to facilitate construction of Bloomington’s Bicentennial gateway and associated curb and sidewalk improvements beginning Aug. 5.

The Board of Public Works at their July 30, 2024 meeting approved periodic lane closures on North College Avenue and North Walnut Street for contractor Reed & Sons of Bloomington, Ind. to unload materials and equipment. The cut-through segment of Old State Road 37 between North College and North Walnut will close Aug. 5 and will remain closed during the gateway construction and site improvement work. Completion is scheduled for late 2024. 

Sidewalks at the north end of Miller-Showers Park, 1500 N. College Ave., will temporarily close during gateway construction. Detours will be provided for the closed routes.

The Board of Park Commissioners at their June 25, 2024 meeting approved an addendum to a contract with Reed & Sons to prepare the site on the north side of Miller-Showers Park for the Bicentennial gateway. Reed & Sons was also awarded a second contract to fabricate and install the limestone gateway wall.

Bo-mar Industries of Beech Grove, Ind. designed the metal lettering and LED lighting for the limestone gateway, and was awarded a contract for its fabrication and installation. 

The Bicentennial gateway is a wall approximately 52′ long and 10′ high, composed of stacked limestone blocks and the word “Bloomington” in backlit letters mounted to the limestone.

The Bloomington Arts Commission (BAC) will solicit design proposals for an additional public art piece located about 60 feet north of the gateway wall. The BAC will receive $125,000 from the Bicentennial Bond fund to solicit, select, and install a piece of public art in this location. Further announcements on this art piece will be made by the BAC.

Funding for the Bicentennial Gateway comes from a series of municipal bonds approved by a vote of the City Council in October 2018. A total of $1.25 million was earmarked for the design and construction of the city gateway. With the exclusion of the additional funds to the BAC, which will come from proceeds of the same Bicentennial Bond account, the project is expected to remain within the original budget.

Bicentennial Gateway Project Timeline

  • The Bloomington Common Council on October 31, 2018, approved the sale of $10 million in bonds for a variety of Bicentennial projects, including the construction, art, and landscaping of four to six gateways to the City. A total of $1.25 million was set aside for the development and installation of the gateways.
  • The Board of Park Commissioners on July 23, 2019, approved a contract with Indianapolis-based Rundell Ernstberger Associates (REA) for $45,800 to complete conceptual design work on the Bicentennial gateways. Four potential gateway locations were identified: Arlington pedestrian bridge over State Road 45/46; Bloomfield Road at Twin Lakes Sports Park; State Road 46 and East Third Street; and the traffic island north of Miller-Showers Park.
  • Parks and Recreation held a public open house December 15, 2019, to unveil the proposed concepts for three signature gateways: At Miller-Showers Park, on the Arlington pedestrian bridge on State Road 45/46, and Bloomfield Road near Twin Lakes Sports Park. The East Third Street site was eliminated from consideration, as it was located on private land. The conceptual designs included the proposed size, construction materials, themes, graphic features and architectural and landscape elements. A total of 34 public comments about the gateway concepts were received online between December 10, 2019, and February 10, 2020.
  • REA presented a Bicentennial gateway project update to the Board of Park Commissioners at their regular meeting on April 28, 2020. The three proposed gateway designs incorporated input from the public, Parks and Recreation staff, and City administration.
  • Parks and Recreation staff restarted the Bicentennial Gateway project after it was halted during the COVID-19 pandemic. Staff reviewed REA’s conceptual designs for the three gateway sites and determined the estimated costs to be over budget. At their May 22, 2022 meeting, the Board of Park Commissioners approved an additional contract with REA for $133,925 for two, scaled-back gateway designs at Miller-Showers Park and the Arlington pedestrian bridge.
  • Final schematic concepts of the two gateway sites were presented to the Board of Park Commissioners at their December. 13, 2022 meeting. A public open house was held December 15, and an additional 59 people submitted feedback and comments regarding the gateway designs online between December 16, 2022, and January 6, 2023.
  • The Indiana Department of Transportation in spring 2023 informed the City of its plans to replace the Arlington pedestrian bridge in the next 10 years. Staff eliminated the Arlington pedestrian bridge from consideration as a gateway site due to its limited lifespan.
  • A contract for $395,105 with bo-mar Industries for the structural design, fabrication, and installation of the Bicentennial gateway at Miller-Showers Park was approved by the Board of Park Commissioners on May 16, 2023. To date, $32,628 has been paid to bo-mar Industries for the structural engineering and associated design work of the gateway element.
  • A contract for $575,000 with Reed & Sons Construction for site work necessary for the installation of the gateway, and sidewalk and paving improvements to the surrounding area, was approved by the Board of Park Commissioners on July 27, 2023. To date, $13,759 has been paid to Reed & Sons Construction for project startup costs.
  • Parks and Recreation issued a news release September 5, 2023 announcing the fall 2023 installation timeline for the monolith-style Bicentennial Gateway at Miller-Showers Park.
  • The Board of Public Works considered but did not act on requests to issue a Right of Way Permit for construction of the project at their September 12, September 26, and October 10 (2023) meetings.
  • The City released an update October 27, 2023 announcing the modification of the timeline for fabrication and installation of the gateway, to allow additional time for public input and feedback.
  • The missing 120-foot section of sidewalk in front of the former Steak N’ Shake restaurant at 1919 N. College Ave. was installed in November 2023 to improve connectivity in the gateway area and allow appropriate pedestrian detours during future phases of construction.
  • The City released an update November 30, 2023 asking for additional feedback on a redesigned concept for the North Gateway. The new design concept called for a horizontal rather than vertical configuration, with the gateway constructed of limestone rather than fabricated metal. A total of 279 feedback submissions were collected between November 30, 2023 and December 15, 2023 for consideration in the development of a final design concept.
  • The City announced January 22, 2024 the new north gateway design would incorporate stacked limestone blocks approximately 10′ high with the word “Bloomington” in letters mounted to the limestone. The final design also incorporated space for a public art installation, to be selected in collaboration with the Bloomington Arts Commission.
  • A contract addendum for $42,300 with Rundell Ernstberger Associates (REA) was approved by the Board of Park Commissioners January 23, 2024. The addendum included development of both the final design into construction documents, and the platform and dimensions for the public art installation.
  • The Bloomington Arts Commission Public Art Subcommittee at their regular meeting Feb. 9, 2024, heard a Gateway project update from Parks and Recreation Administrator Tim Street. The subcommittee is planning a visit to the Gateway site north of Miller-Showers Park to view the location in preparation for developing requests for proposals for a public art installation.
  • A contract addendum for $79,462.44 in additional contract value (original contract was for $575,000) with Reed & Sons was approved by the Board of Park Commissioners June 25, 2024. The addendum included additional sidewalk construction as well as site modifications to accommodate the updated gateway design.
  • The Board of Park Commissioners on June 25, 2024 also approved a separate contract for $249,750 with Reed & Sons to construct the actual gateway element, a horizontal wall of limestone blocks. 
  • The Board of Park Commissioners on June 25, 2024 also approved a contract with bo-mar Industries to design and construct the powder-coated aluminum lettering and LED lighting spelling “BLOOMINGTON” and to install the lettering on the limestone gateway.
  • The Board of Public Works on July 30, 2024 approved a request for periodic right-of-way closures on North College Avenue and North Walnut Street, and the temporary closure of the Old State Road 37 cut-through between North College and North Walnut, to facilitate construction of the gateway and associated sidewalk and curb improvements and infrastructure installation.

In all, the cost impacts of the redesign include:

  • $47,766.87 – Reed & Sons change order
  • $249,750 – Limestone wall construction
  • $65,000 – bo-mar industries lettering & lighting
  • $42,300 – additional design fees for REA (approved December 2023)
  • ($362,477.00) – this amount was recouped from the original contract with bo-mar industries for $395,105 for the vertical gateway element. $32,628 was not recoverable.

This brings the net impact of the redesign to $42,339.87 and brings the total project cost to $1.23 million out of an original budget of $1.25 million. However, as part of the redesign, Parks and Recreation also worked with the Bloomington Arts Commission (BAC) to include a separate art element. The BAC will receive $125,000 from the Bicentennial Bond Series C fund to solicit, select, and install a piece of public art in this location. Enough additional funds remain in this bond fund from the original issuance and interest accrued in the intervening years to pay for the art element through the BAC without negatively impacting other projects.