BLOOMINGTON—The Bicentennial Gateway at Miller-Showers Park, 101 W. 17th St., is nearing completion. The gateway, surrounding landscaping, sidewalks, and road work are scheduled to be finished by mid-November.
The Bicentennial Gateway is a wall approximately 52′ long and 10′ high, composed of stacked limestone blocks and the word “Bloomington” in backlit letters mounted to the limestone. bo-mar Industries in Indianapolis is fabricating the powder-coated aluminum letters. They are slated for installation when crushed limestone surfacing and park benches are in place around the gateway.
The final landscaping work, including tree planting, will begin the last week of October. Plans call for more than 20 trees to be planted in the median around the gateway. Tree species include serviceberry, redbud, yellowwood, black gum, and white oak.
The cut-through is scheduled to be re-opened when it is paved, likely after the first week in November.
The Bloomington Arts Commission (BAC) will solicit design proposals for an additional public art piece about 60 feet north of the gateway. The BAC will receive $125,000 from the Bicentennial Bond fund to solicit, select, and install a piece of public art in this location. The BAC will make further announcements on this art piece.
Funding for the Bicentennial Gateway comes from a series of municipal bonds approved by the City Council in October 2018. A total of $1.25 million was earmarked for the design and construction of the city gateway. The additional funds to the BAC, which will come from proceeds of the same Bicentennial Bond account, will be excluded, so the project is expected to remain within the original budget.
Bicentennial Gateway Project Timeline
- The Bloomington Common Council approved the sale of $10 million in bonds on October 31, 2018, for various Bicentennial projects, including the construction, art, and landscaping of four to six gateways to the City. A total of $1.25 million was set aside to develop and install the gateways.
- The Board of Park Commissioners approved a $45,800 contract with Indianapolis-based Rundell Ernstberger Associates (REA) on July 23, 2019, to complete conceptual design work on the Bicentennial gateways. Four potential gateway locations were identified: the Arlington pedestrian bridge over State Road 45/46, Bloomfield Road at Twin Lakes Sports Park, State Road 46 and East Third Street, and the traffic island north of Miller-Showers Park.
- Parks and Recreation held a public open house on December 15, 2019, to unveil the proposed concepts for three signature gateways: Miller-Showers Park, on the Arlington pedestrian bridge on State Road 45/46, and Bloomfield Road near Twin Lakes Sports Park. The East Third Street site was eliminated from consideration, as it was located on private land. The conceptual designs included the proposed size, construction materials, themes, graphic features, and architectural and landscape elements. Thirty-four public comments about the gateway concepts were received online between December 10, 2019, and February 10, 2020.
- REA presented a Bicentennial gateway project update to the Board of Park Commissioners at their April 28, 2020, meeting. The three proposed gateway designs incorporated input from the public, Parks and Recreation staff, and City administration.
- Parks and Recreation staff restarted the Bicentennial Gateway project after it was halted during the COVID-19 pandemic. Staff reviewed REA’s conceptual designs for the three gateway sites and determined the estimated costs to be over budget. At their May 22, 2022, meeting, the Board of Park Commissioners approved an additional contract with REA for $133,925 for two scaled-back gateway designs at Miller-Showers Park and the Arlington pedestrian bridge.
- The final schematic concepts of the two gateway sites were presented to the Board of Park Commissioners at their December 13, 2022 meeting. A public open house was held on December 15, and an additional 59 people submitted feedback and comments regarding the gateway designs online between December 16, 2022, and January 6, 2023.
- In spring 2023, the Indiana Department of Transportation informed the City of its plans to replace the Arlington pedestrian bridge within the next 10 years. Staff eliminated the bridge from consideration as a gateway site due to its limited lifespan.
- The Board of Park Commissioners approved a contract for $395,105 with bo-mar Industries for the structural design, fabrication, and installation of the Bicentennial gateway at Miller-Showers Park on May 16, 2023. To date, $32,628 has been paid to bo-mar Industries for the gateway element’s structural engineering and associated design work.
- The Board of Park Commissioners approved a contract for $575,000 with Reed & Sons Construction for site work necessary for the installation of the gateway and sidewalk and paving improvements to the surrounding area on July 27, 2023. To date, $13,759 has been paid to Reed & Sons Construction for project startup costs.
- Parks and Recreation issued a news release on September 5, 2023, announcing the fall 2023 installation timeline for the monolith-style Bicentennial Gateway at Miller-Showers Park.
- The Board of Public Works considered but did not act on requests to issue a right-of-way permit for the project’s construction at its September 12, September 26, and October 10 (2023) meetings.
- The City released an update on October 27, 2023, announcing the modification of the timeline for fabricating and installing the gateway to allow additional time for public input and feedback.
- The missing 120-foot section of sidewalk in front of the former Steak N’ Shake restaurant at 1919 N. College Ave. was installed in November 2023 to improve connectivity in the gateway area and allow appropriate pedestrian detours during future construction phases.
- The City released an update on November 30, 2023, asking for additional feedback on a redesigned concept for the North Gateway. The new design concept called for a horizontal rather than vertical configuration, with the gateway constructed of limestone rather than fabricated metal. A total of 279 feedback submissions were collected between November 30, 2023, and December 15, 2023, for consideration in the development of a final design concept.
- The City announced on January 22, 2024, that the new north gateway design would incorporate stacked limestone blocks approximately 10′ high with the word “Bloomington” in letters mounted to the limestone. The final design also incorporated space for a public art installation, to be selected in collaboration with the Bloomington Arts Commission.
- The Board of Park Commissioners approved a contract addendum for $42,300 with Rundell Ernstberger Associates (REA) on January 23, 2024. The addendum included developing the final design into construction documents and the platform and dimensions for the public art installation.
- The Bloomington Arts Commission Public Art Subcommittee, at its regular meeting on Feb. 9, 2024, heard a Gateway project update from Parks and Recreation Administrator Tim Street. The subcommittee is planning to visit the Gateway site north of Miller-Showers Park to view the location in preparation for developing requests for proposals for a public art installation.
- The Board of Park Commissioners approved a contract addendum with Reed & Sons for $79,462.44 in additional contract value (the original contract was for $575,000) on June 25, 2024. The addendum included additional sidewalk construction and site modifications to accommodate the updated gateway design.
- The Board of Park Commissioners also approved a separate contract for $249,750 with Reed & Sons to construct the actual gateway element, a horizontal wall of limestone blocks, on June 25, 2024.
- The Board of Park Commissioners also approved a contract with bo-mar Industries on June 25, 2024, to design and construct the powder-coated aluminum lettering and LED lighting spelling “BLOOMINGTON” and install the lettering on the limestone gateway.
In all, the cost impacts of the redesign include:
- $47,766.87 – Reed & Sons change order
- $249,750 – Limestone wall construction
- $65,000 – bo-mar Industries lettering & lighting
- $42,300 – additional design fees for REA (approved December 2023)
- ($362,477.00)—This amount was recouped from the original contract with Bo-Mar Industries for $395,105 for the vertical gateway element. $32,628 was not recoverable.
This brings the net impact of the redesign to $42,339.87 and the total project cost to $1.23 million out of an original budget of $1.25 million. However, as part of the redesign, Parks and Recreation also worked with the Bloomington Arts Commission (BAC) to include a separate art element. The BAC will receive $125,000 from the Bicentennial Bond Series C fund to solicit, select, and install a piece of public art in this location. Enough additional funds remain in this bond fund from the original issuance and interest accrued in the intervening years to pay for the art element through the BAC without negatively impacting other projects.
- The Board of Public Works on July 30, 2024, approved a request for periodic right-of-way closures on North College Avenue and North Walnut Street and the temporary closure of the Old State Road 37 cut-through between North College and North Walnut to facilitate construction of the gateway and associated sidewalk and curb improvements and infrastructure installation.
- The Board of Park Commissioners on Oct. 15, 2024, approved an addendum for $11,588.41 to the June 25 contract with Reed & Sons for Bicentennial Gateway site improvements. When excavating the footer for the gateway element, unsuitable soils were found, necessitating additional excavation, subgrade replacement, and concrete forming. A stormwater access lid was reset to comply with City of Bloomington Utilities standards.