Traffic Switches on Southport Road expected Sunday night

INDIANAPOLIS –  Crews will begin switching Southport Road/State Road 37 traffic into a new phase starting Sunday night to allow for the construction of mainline I-69 and completion of the Southport Road interchange.

During this time, access to S.R. 37 from Old Southport Road west of the highway and the existing signal and access to S.R. 37 at Banta Road in Marion County will be removed.

Southport Road to Southbound S.R. 37

The new southbound on-ramp from Southport Road to S.R. 37 will open with a temporary traffic signal to allow for seamless entry onto S.R. 37. The traffic signal will be synchronized with the existing signal at the intersection of S.R. 37 and Old Southport Road.

Southport Road to Northbound S.R. 37

During the seven-day closure the Southport Road on-ramp to northbound S.R. 37 will remain closed as crews finish the ramp and tie it into the new northbound travel lanes. During this time, northbound motorists will be detoured to Harding Street to S.R. 37. 

Northbound S.R. 37 to Southport Road

S.R. 37 northbound to Southport Road will use a portion of the new exit ramp followed by a stretch of temporary pavement that connects to Old Southport Road. Be sure to slow down to safely exit S.R. 37.

Southbound S.R. 37 to Southport Road

The southbound S.R. 37 ramp onto Southport Road will remain open throughout the duration of the closure.

At the conclusion of the seven-day closure all Southport Road ramps will be open and all S.R. 37 traffic will be moved onto new pavement.  The speed limit throughout this section of the I-69 Finish Line project remains 45 miles per hour.